A bathroom remodel cost calculator estimates what a renovation may cost, either as a quick range from the bathroom size and finish level or as an itemized budget with labour and a contingency reserve.
Bathroom Remodel Cost Calculator
Estimate the cost of a bathroom remodel or renovation — a quick estimate by size and finish level, or an itemized budget.
The starting values are an 8 ft by 5 ft bathroom at the mid-range level of $250 per ft², with no local adjustment. The itemized mode starts with a $900 vanity, $350 toilet, $1,500 tub or shower, $450 faucets, $1,200 tile, $500 lighting, $300 for mirror and accessories, $6,000 labour and a 10% contingency. These are example prices, not quotes, so replace them with figures from your own area.
What the bathroom remodel cost calculator estimates
The quick estimate works from floor area and finish level. It returns an estimated cost, a lower figure 20% below it and an upper figure 20% above, so you see a range rather than one number. The itemized budget takes your own prices for the main items and labour, then adds a contingency to give a total, with materials and labour shown separately. Use the quick mode to test whether a project is realistic, and the itemized mode once you have prices.
The quick estimate formula
Floor area = Length × Width
Estimated cost = Floor area × Cost per ft² × (1 + Local adjustment)
Lower estimate = 0.8 × Estimated cost
Upper estimate = 1.2 × Estimated cost
Where:
- Cost per ft² = the finish level you choose: $100 for a basic refresh, $250 for a mid-range remodel or $450 for high-end work
- Local adjustment = a percentage for your area, for example +20 for a high-cost city or −15 for a low-cost one
Worked example: a 9 ft by 6 ft bathroom
Floor area = 9 × 6 = 54 ft²
Take the mid-range level with a +15% local adjustment:
Estimated cost = 54 × 250 × 1.15 = $15,525
Lower estimate = 0.8 × 15,525 = $12,420
Upper estimate = 1.2 × 15,525 = $18,630
So a mid-range remodel of this room in a higher-cost area is budgeted at roughly $12,400 to $18,600, with $15,500 as the central figure.
The itemized budget formula
Subtotal = Vanity + Toilet + Tub or shower + Faucets + Tile + Lighting + Mirror and accessories + Labour
Total = Subtotal × (1 + Contingency)
Materials = Subtotal − Labour
The contingency is a percentage you enter, written as a number such as 10 or 15. It is applied to the whole subtotal, labour included.
Worked example: an upgraded bathroom
Suppose a $1,400 vanity, $350 toilet, $2,200 tub or shower, $450 faucets, $1,800 tile, $500 lighting, $300 for mirror and accessories, and $7,500 labour, with a 15% contingency.
Subtotal = 1,400 + 350 + 2,200 + 450 + 1,800 + 500 + 300 + 7,500 = $14,500
Materials = 14,500 − 7,500 = $7,000
Total = 14,500 × 1.15 = $16,675
Labour is $7,500 of the $14,500 subtotal, about 52%, and the contingency adds $2,175 as a reserve.
Why a per-square-foot figure only goes so far
Fixtures, plumbing and labour do not shrink in proportion to the room, so small bathrooms cost more per square foot than large ones. One 2026 cost guide prices a mid-range remodel of a 5 ft by 7 ft bathroom at just over $24,000, close to $690 per ft². The $250 level gives only $8,750 for the same 35 ft². Published figures differ a lot because they define scope differently, so treat the quick estimate as a starting range and use the local adjustment or the itemized mode to bring it closer to your quotes.
What pushes a remodel cost up
Scope matters most. The same guide lists moving plumbing or wiring, converting a half bath to a full bath, working on a second floor or basement bathroom, and choosing marble or quartz over ceramic or porcelain as the main cost drivers. It also puts labour at 45% to 65% of a bathroom budget and permits at $400 to $750 or more. The itemized mode has no separate permit line, so add permit fees to the labour field or cover them with the contingency.
Reading the lower and upper estimates
The lower and upper figures sit a fixed 20% either side of the central estimate. They are a planning band, not a prediction, so a project with major plumbing changes can land outside it. Use the upper figure when deciding whether you can afford the project, and treat the lower figure as realistic only when the scope is simple and your quotes are already in hand.
Setting the contingency
The default of 10% suits a straightforward swap of fixtures. Opening walls and floors can uncover rot, outdated wiring or uneven subfloors. A tile cost guide suggests keeping 10% to 20% of the budget in reserve for hidden damage, so raise the contingency to 15% or 20% for an older bathroom or one with a history of leaks.
Frequently asked questions
How much does a bathroom remodel cost per square foot?
The calculator uses illustrative levels of $100, $250 and $450 per ft² for a basic refresh, a mid-range remodel and high-end work. They are planning defaults, not quotes. Small bathrooms often cost more per square foot because fixtures and labour do not shrink with the room, so check the result with the itemized mode.
How do I estimate a bathroom remodel by size?
Multiply length by width to get the floor area, multiply by the cost per ft² for your finish level, then apply a local adjustment. A 54 ft² bathroom at $250 with +15% comes to $15,525, with a range of $12,420 to $18,630.
What contingency should I add to a bathroom remodel?
The itemized mode defaults to 10% of the subtotal. A tile cost guide suggests holding 10% to 20% in reserve for hidden damage, so use a higher figure for an older bathroom or one where water damage is possible.
What does the itemized bathroom budget leave out?
It covers the vanity, toilet, tub or shower, faucets, tile, lighting, mirror and accessories, and labour. Permits, design fees, demolition disposal and plumbing relocation have no separate line, so include them in the labour field or in the contingency.