This calculator estimates a painting job in two ways. In the by-area mode you enter the area, the number of coats, the paint coverage and price, a labour rate per square foot and a lump sum for supplies. In the by-hours mode you enter a painting speed and an hourly rate instead. Both round the paint up to whole gallons, and every price in the tool is an example to replace with your own quote.
Painting Cost Calculator
Estimate a painting job: paint cost, labour by area or by hours, prep and supplies.
How the painting cost is calculated
By area
Gallons = round up (area × coats ÷ coverage per gallon)
Paint cost = gallons × price per gallon
Labour = area × labour rate per ft²
Total = paint cost + labour + supplies
By hours
Labour hours = area ÷ painting speed × coats
Total = labour hours × hourly rate + gallons × price per gallon
Where:
- Area is the surface to paint, in square feet.
- Coverage is the area one gallon covers in one coat, printed on the can.
- Painting speed is in square feet per hour for one coat.
- Supplies cover tape, primer and repairs in the by-area mode. The by-hours mode does not add a supplies line.
Worked examples
Example 1: by area, the starting values
800 ft², 2 coats, 350 ft² per gallon, $45 per gallon, labour at $2 per ft² and $100 for supplies:
Gallons = 800 × 2 ÷ 350 = 4.57, so 5 gallons
Paint = 5 × 45 = $225
Labour = 800 × 2 = $1,600
Total = 225 + 1,600 + 100 = $1,925
Example 2: by hours, the starting values
800 ft², a speed of 150 ft² per hour per coat, 2 coats, $50 per hour and $45 per gallon of paint:
Hours = 800 ÷ 150 × 2 = 10.67 h
Labour = 10.67 × 50 = $533.33
Paint = 5 gallons × 45 = $225
Total = $758.33
Example 3: a larger exterior job by area
1,500 ft² of fence and siding, 2 coats, 400 ft² per gallon, $38 per gallon, labour at $1.80 per ft² and $250 for supplies:
Gallons = 1,500 × 2 ÷ 400 = 7.5, so 8 gallons
Paint = 8 × 38 = $304
Labour = 1,500 × 1.80 = $2,700
Total = 304 + 2,700 + 250 = $3,254
Comparing the two modes
The two starting totals, $1,925 and $758, are far apart only because the example labour assumptions differ. To make them comparable, convert the hourly rate into a rate per square foot of surface:
Labour rate per ft² = hourly rate × coats ÷ speed
= 50 × 2 ÷ 150 = $0.67 per ft²
Entering $0.67 in the by-area mode gives labour of 800 × 0.67 = $533, the same as the by-hours result. If your painter quotes $2 per ft², that is a much higher cost per hour than $50, so ask what the quote includes, such as preparation, trim and cleanup.
What changes the total
Number of coats
Coats multiply both the paint and the hours. A third coat in example 1 needs 800 × 3 ÷ 350 = 6.86, so 7 gallons, which is $315 of paint instead of $225.
Coverage
Coverage depends on the paint and the surface. The tool hint says most wall paints cover 350 to 400 ft² per gallon, and the can gives the figure for your product. Rough or porous surfaces take more.
Rounding to whole gallons
Paint is bought by the gallon, so the tool rounds up. In example 3 the exact need is 7.5 gallons, and you buy 8.
What the estimate leaves out
- Primer and surface repair beyond the supplies you enter.
- Trim, doors and ceilings, which you can add as separate areas.
- Scaffolding, ladders and equipment hire.
- Travel, minimum charges and tax.
For the paint quantity of one room, use a room paint calculator. For the whole estimate, replace each placeholder with a written quote.
Frequently asked questions
How is the cost of painting calculated here?
In the by-area mode the tool adds paint, labour at a rate per square foot, and supplies. With the starting values the total is $1,925 for 800 ft² at two coats.
Are the prices real costs?
No. The labour rates and paint prices are examples. Replace them with quotes from your painter and supplier.
How do I convert an hourly rate to a rate per square foot?
Multiply the hourly rate by the number of coats and divide by the painting speed. $50 per hour, 2 coats and 150 ft² per hour gives about $0.67 per ft².
Why does the tool round paint up?
Paint is sold by the gallon, so any part of a gallon needs a whole one. 7.5 gallons needs 8.
Does the by-hours mode include supplies?
No. It adds the labour hours at your rate and the paint. Add supplies yourself if you need them.
How many coats should I enter?
The tool starts with 2. The number you need depends on the paint, the surface and the old colour, so follow the instructions on your product.